LB Nagar Kamineni Flyover Highlights

lbnagar kamineni flyover hyderabad
SRDP - Hyderabad Beautification Programme:
Srikanth

Reviewed by:
Rating:
5
On August 7, 2018
Last modified:August 8, 2018

Summary:

LB Nagar Kamineni LHS Flyover Project Saves in travel time and hence savings in vehicle operation costs like fuel etc.,Reduction in pollution and noise levels due to reduction in waiting/ travel time at the junction. #HyderabadBeautificationProject

LB Nagar Kamineni Flyover(Kamineni LHS Flyover)

A new technology has been introduced by practicing engineers in India, that too in Hyderabad by constructing Kamineni flyover(LB Nagar Flyover) in 16 months with prestressed post-tensioned for substructure(vertical segments). A move forward in the right direction.

Project Name : Construction of multilevel / Grade separators at Four junctions at LB Nagar and surroundings in Hyderabad under Package – II of SRDP(Strategic Road Development Programme) Phase I

Structure: LHS Flyover at Kamineni Junction
Project cost: Rs. 448 Crores
Cost of LHS Flyover: Rs. 49.00 Crores

LB Nagar Kamineni Hospital Flyover – SALIENT FEATURES

  • Total length : 940m
  • Length of Viaduct portion: 380m
  • Standard spans : 330m (11 x 30m)
  • Obligatory span : 50m (1 x 50m)
  • Length of Ramps : 560m
  • Srisailam Side : 195m
  • Secunderabad Side : 365m
  • Total Width of Flyover : 12m
  • Min. Vertical clearance under flyover : 5.5m
  • Carriageway details : 11m, 3 lane one way

Source & Image Credits to P V Krishna Rao EE

Kamineni LHS flyover Viaduct

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

lbnagar kamineni flyover - hyderabad

Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image...
  • Substructure: Open foundation, single pier & pier cap with pre-cast post-tensioned pier and pier cap segments
  • Superstructure:
    • Standard spans: Pre-cast post-tensioned I-girders with partially precast & cast
    In-situ RCC deck slab along with precast crash barrier.
    • Obligatory spans: Fabricated steel plate composite girders with partially
    precast & cast-in-situ RCC deck slab along with precast crash barrier

 

Approaches
RE Wall structure with precast friction slab & crash barrier.

Pavement

  • CC wearing coat on Viaduct portion
  • Continuously Reinforced Concrete Pavement (CRCP) on Approach ramps

Miscellaneous

  • MS Handrailing
  • LED lighting
  • Anti-carbonate painting

Traffic Solution Details for Kamineni Junction (Both flyovers & 2-way Underpass)

  • Traffic Solution: 89 %
  • Peak hour PCU in 2015 without metro: 10324
  • Peak hour PCU in 2015 with metro: 6504
  • Projected Peak hour PCU in 2034: 16209

Advantages of LB Nagar Surroundings SRDP Programme

  • Free flow of traffic from Srisailam, Owisi, and Vijayawada to Secunderabad through this Flyover
  • Kamineni Junction will be conflict-free once RHS flyover on ring road and Underpass on siris – mansoorabad road is constructed
  • Saving in travel time and hence savings in vehicle operating costs like fuel etc.,
  • Reduction in pollution and noise levels due to the reduction in waiting/ travel time at the junction

Technology Used

  • Precast and post-tensioned technology is adopted in major elements of substructure and superstructure by casting in casting yard and erecting them at the site.
  • RCC Precast technology is used in minor elements of structure like crash barriers, friction slabs and slab panels etc.,
  • This technology for the substructure is used for the 1st time in INDIA.
  • By adopting this technology
    • Work at the site has been confined for the erection and stressing activities only
    • Formwork and staging are avoided at site for Pier, Pier Cap, Deck Slab and Crash barriers
    • A significant amount of time was saved
    • Reduced the factor of risk of accidents by mechanization to a large extent and considerable reduction in manpower
    • Inconvenience to the at-grade traffic has been significantly reduced

SRDP is taken up at an outlay of about 23,000 Crores to comprehensively solve Traffic Problems duly providing Grade Separators /Flyovers at 54 junctions, Elevated Corridor/Skyways of 111 kms, Major Corridor Development 166 kms, Major Road Development 348 kms

Works Grounded /Agencies ready – about Rs.2982.64 Crores

TENTATIVE DATES FOR COMPLETION OF PROJECTS

#1 L.B.Nagar Corridor – Rs.448 Crores

  1. Chintalkunta underpass – Completed & inaugurated on 01.05.2018
  2. Kamineni LHS Flyover – Inauguration on 8th August 2018
  3. LB Nagar LHS Flyover – September 2018
  4. LB Nagar LHS underpass – December 2018
  5. Bairamalguda RHS Flyover – March 2019
  6. Kamineni RHS Flyover – March 2019
  7. LB Nagar RHS Flyover – June 2019

#2. Mind Space Biodiversity Corridor –Rs.379 Crores

  1. Ayyappa Society Underpass – Completed & inaugurated on 03.01.2018
  2. Mind Space underpass – Completed & inaugurated on 28.04.2018
  3. Mind Space flyover – August 2018
  4. Bio-Diversity flyover – March 2019
  5. Rajiv Gandhi Statue Flyover – December 2018

#3. Durgam Cheruvu Cable-Stayed Bridge –Rs.184 Crores -March 2019

#4. Road No.45 Elevated Corridor –Rs.150 Crores – September 2019

#5. Shaikpet Elevated Corridor – Rs.333.55 Crores -December 2019

#6. Kothaguda Grader Separators –Rs. 263.09 Crores -December 2019

#7. Balanagar Grade Separator –Rs. 387 Crores – September 2019

#8. Owaisi Hospital and Bahadurpura – Rs.132 Crores – September 2019

#9. Amberpet 6 No. flyover – Rs.270 Crores -December 2019

#10. Flyovers around KBR Park –Rs.436 Crores -To be grounded after GoI Environmental Clearance